Resurfacing of Hindon Lane

09/05/2023

The Parish Council has been informed that the works to resurface Hindon Lane by Wiltshire Council’s contractors will start on Tuesday 9th May and will be completed on Wednesday 17th May. The work will be carried out between 09:00 and 15:00 hours on weekdays under a temporary road closure and the road will be open as normal outside of these hours.The works comprise repairs to the existing carriageway, the installation of new road markings and the adjustment of surface ironwork. There will be advanced information signs erected on site giving confirmed start dates. A letter drop to all residents and businesses within the closure was completed last week and the contractor will maintain pedestrian access for residents for the duration of the works.Residents are asked to avoid the area during the closure times if possible.